The case of import of automatic chip mounter by imton

time:2022-10-17 15:23

The imported goods need to be coded and classified according to the specific conditions of the goods, and the regulatory conditions, tax rates and other information of the goods can be known through the accurate customs codes after classification.

This case is about the import of new equipment. We need to confirm whether the equipment needs to apply for an automatic import license, whether it involves a "key mechanical and electrical licenses", etc. The difficulty involved in customs clearance at domestic ports is inspection.

Imported article: Automatic chip mounter

Quantity: 1 container

Country of origin: Japan

Transportation mode: water transportation

Import route: Japan - Shanghai

Service: door-to-door (foreign loading - whole journey transportation - import customs clearance)

Automatic placement machine is a scientific instrument used in the field of information science and system science.

Many enterprises did not handle the relevant import documents in advance before importing equipment, and rushed to ship the equipment to China. When the goods arrived at the port, they were reminded by the customs. The documents were incomplete and could not be declared, resulting in a large number of warehouse rent, container rent and customs fines at the terminal shipping company. What is more serious is that the enterprise cannot deliver the goods, resulting in huge liquidated damages.

To avoid the above problems, we need to sort out the materials in advance and prepare for customs declaration.

Difficulties:

1. Domestic customs inspection;

2. Domestic transportation;

After the shipment of goods is completed, the fleet can be arranged to take the goods to the port for export customs declaration and to Shanghai port by sea.

After the goods arrive at the port, the materials shall be reviewed again, and the declaration shall be made after confirming that the materials are correct.

Before customs inspection, the list of equipment loaded in containers shall be sorted out again, and relevant documents shall be sorted out, so as to solve the problems of customs inspection in a short time.

After the customs clearance of equipment is completed, air cushion vehicles shall be arranged for transportation according to the requirements.